The below Insruction Help You to Improve Your Design
The completed design package must clearly convey the design
intent. The contract documents provide the information
necessary to implement the design. These documents include:
1. Statement of Work (SOW) -
A brief but thorough
description of the work to be performed by the contractor. The
SOW is used by the contracting agent to synopsize the project
in the bid advertisement.
description of the work to be performed by the contractor. The
SOW is used by the contracting agent to synopsize the project
in the bid advertisement.
2. Architectural Floor Plan - Demolition plans, new floor plans, and reflected ceiling plans.

which finishes are used on specific interior surfaces, and the
list identifying each finish by pattern, color, number, brand
and manufacturer.
4. Finish Floor Plan - A drawing typically used to clarify the
placement of patterns, borders, or combinations of floor finishes
in an area.
placement of patterns, borders, or combinations of floor finishes
in an area.
5. Elevations, Sections, and Details - Drawings used to
further clarify a design feature. Elevations are drawings which
typically illustrate placement of wallcovering as well as height
of chair rails, bumper guards, plumbing fixtures, and other
design features permanently attached to the walls. Sections
and details generally illustrate how a particular feature is
constructed or attached to another surface or feature, and of
what generic materials it is made.
further clarify a design feature. Elevations are drawings which
typically illustrate placement of wallcovering as well as height
of chair rails, bumper guards, plumbing fixtures, and other
design features permanently attached to the walls. Sections
and details generally illustrate how a particular feature is
constructed or attached to another surface or feature, and of
what generic materials it is made.
6. Miscellaneous Drawings - Electrical layouts, enlarged floor
plans of rest rooms and repetitive areas (e.g., dorm rooms),
and construction drawings for built-in cabinetry, etc.
plans of rest rooms and repetitive areas (e.g., dorm rooms),
and construction drawings for built-in cabinetry, etc.
7. Furniture Floor Plan - Scaled layouts showing placement
of existing and new furniture and equipment. Separate
drawings may be required for conventional furniture (modular
or “freestanding” items) and systems furniture (panel mounted
workstations, generally prewired). These drawings provide
references for changes or decisions required during project
construction.
of existing and new furniture and equipment. Separate
drawings may be required for conventional furniture (modular
or “freestanding” items) and systems furniture (panel mounted
workstations, generally prewired). These drawings provide
references for changes or decisions required during project
construction.

systems furniture panels, electrical connections and power
layouts, and components. Installation plans and/or elevations
may also be required for artwork and signs.
9. Furnishings Specifications - Technical product
information, including as necessary item name, size, color,
fabric or finish, fire rating, brand and manufacturer, source,
quantity, photo or catalog cut, and cost.
information, including as necessary item name, size, color,
fabric or finish, fire rating, brand and manufacturer, source,
quantity, photo or catalog cut, and cost.
10. Furnishings Cost Estimates - Line item extensions of
item costs may need to be separated by item category or by
room or area for phased purchasing.
item costs may need to be separated by item category or by
room or area for phased purchasing.
11. Furnishings Order Forms - The actual forms required by
the user to order the items.
the user to order the items.
0 comments: